Oyo govt assures quality work on Iseyin-Saki road rehabilitation

The Oyo State Government has assured residents of the quality execution of the ongoing rehabilitation of the 83.82-kilometre Iseyin-Okaka-Saki Road.

 

The state government, in a statement on Thursday, said the project is under strict supervision by Resident Engineers from the Ministry of Public Works and Transport.

 

It added that the Commissioner for Public Works and Transport, Prof. Dahud Shangodoyin, alongside a team of engineers, has been conducting regular inspections, including a site visit on February 20, 2025.

 

This assurance follows allegations of poor workmanship on the project, which surfaced in a social media post.

 

However, the government dismissed the claims as unfounded, stating that the rehabilitation is being carried out in line with approved specifications.

 

Prof. Shangodoyin, in the statement, explained that Governor Seyi Makinde had approved a palliative intervention on the road, which includes clearing, turnouts, scarification, and the removal of unsuitable materials.

READ ALSO...  NSIB DG, Oyo Join Forces to Revolutionize Transport Safety

 

Other components of the project involve the provision of a reinforced concrete retaining wall, the supply of sub-base and base course materials, and the laying of a 40mm asphaltic wearing course at critical sections of the road.

 

The statement read, “The Iseyin-Saki Road (83.82km) is a federal road that has undergone multiple rehabilitations by the Federal Roads Maintenance Agency (FERMA). However, the road deteriorated and became nearly impassable.

 

“Despite being a Trunk A road, Governor Makinde, in his commitment to ensuring a smooth commuting experience for residents, directed the state government to undertake rehabilitation work to ease the hardship faced by road users.”

 

According to the commissioner, the project was awarded to a reputable contractor with a track record of executing several projects in the state, and the cost of the ongoing palliative work is being fully borne by the state government.

 

Providing an update on the progress, Shangodoyin noted that asphaltic regulation of the surface from Iseyin to Ipapo has been completed, while asphalt resurfacing between Ipapo and Alaga Road has also been concluded.

READ ALSO...  Breaking: JAMB releases results of 2022 UTME mop-up exam

 

He added that the laying of stone base and asphalting between Okaka and Alaga has been completed, while stone base laying and asphalt resurfacing between Alaga and Baasi is currently ongoing.

 

He stated that the outstanding work includes the laying of stone base and asphalt resurfacing between Baasi and Saki.

 

The commissioner reiterated the government’s commitment to ensuring that the project meets the highest standards and provides long-term relief for commuters.

 

 

NOTE: YOU can join our Online Platform for the News updates by sending your Full name & Location to us on WhatsApp and for your Advert and Publication @ 08072633727

 

YOU CAN READ MORE NEWS UPDATES AND INFO @ https://www.voiceairmedia.com

Akanji Philip

Akanji Philip has been working as a reporter with VOICE AIR MEDIA, both onsite at the head office in Odi-Olowo, Osogbo, and remotely. He has covered events at notable political venues, involving prominent figures such as former Osun Governor Adegboyega Oyetola, current Osun State Governor Senator Isiaka Adetunji Adeleke, former Vice President Professor Yemi Osinbajo, the late Ondo Governor Rotimi Akeredolu, Oyo State Governor Seyi Makinde, and various other representatives and lawmakers. In addition, he has represented the company at various press conferences at police stations and has reported on occasions featuring entertainers and actors, such as Kola Oyewo during Oba-Ile Day in Osun State, among others. -Phone Number: +2349058501092, +2348137827714 -Email: akanjiphilips100@gmail.com

Learn More →